Columbia Gas of Kentucky currently has several pipeline projects in progress, including:

West Clinton Street, Georgetown –
This project includes the replacement of approximately 13,350 feet of main line and the replacement or tie-in of 210 service lines. To date, approximately all of the main line has been replaced and 183 service lines have been replaced.

7th Street, Ironton, Ohio – This project includes the replacement of 10,215 feet of main line and 165 service line replacements or tie-overs. To date, contractors have installed approximately 8,700 feet of the main line and replaced or connected 148 service lines.

Eastover/Westover, Frankfort – This project includes the replacement of 9,400 feet of main line and 204 service line replacements or tie-overs.To date, approximately 8,900 feet of main line has been installed and 139 service lines have been replaced.

2nd Street, Maysville – This project includes the replacement of 3,400 feet of main line and 125 service lines. To date, all of the main line has been installed and 120 service lines have been replaced or tied over.

South Broadway/W. Maxwell, Lexington
This project includes the replacement of 5,235 feet of main line and 106 service lines. To date, contractors have replaced approximately 4,500 feet of main line and replaced or connected 67 service lines.

Hilton/Lexington Street, Ashland –
This project includes the replacement of 6,592 feet of main line and 131 service line replacements or tie-overs. To date, contractors have replaced approximately 3,000 feet of main line and 47 service lines.

Leesway Drive, Lexington -- This project includes the replacement of 1,600 feet of main line and 38 service line replacements or tie-overs. To date, the contractor has installed all of the main line and has replaced or connected 29 service lines.

Euclid Avenue, Lexington -- This project includes the replacement of 6,815 feet of main line and 216 service line replacements or tie-overs. Work on this project began on Clay Avenue, Marquis Avenue and Woodland Avenue and is now moving onto Kentucky Court and Oldham Avenue.  To date, contractors have installed 1,000 feet of main line and replaced or connected 15 service lines.  On-street parking may be impacted at times during the project. No parking signs will be posted when parking is restricted.

Pine Grove, Winchester
-- This project includes the replacement of 2,630 feet of main line and 10 service line replacements or tie-overs. To date, contractors have installed approximately 2,200 feet of new main line.

Winchester Road, Lexington -- This project includes the replacement of 700 feet of main line.  To date, approximately 300 feet of the new main line has been installed.

Upcoming Pipeline Improvement Projects

Pickett Avenue, Frankfort
Walnut Street, Cynthiana
Saint Margaret Drive, Lexington
East Maxwell & High Street, Lexington
Pine Grove, Winchester
Winchester Road, Lexington
Butimer Hill, Frankfort
UK Research Farm, Versailles

For further updates or questions about these projects, please contact Columbia Gas of Kentucky Construction Specialist Bobby Dawes at 859-991-5659.

Natural gas pipelines are the safest form of fuel transportation in the nation. Sometimes, however, failures do occur and it is important for you to know how to respond.

Odor of Gas

Natural gas has a rotten egg or petroleum odor that can alert you to a leak in or around your home. If you smell an odor of gas:

  • Leave the building immediately. Leave the door open and don't use light switches or matches. 
  • Call our 24-hour emergency number at 1-800-432-9515 from a phone outside of the building and wait for our service crew to arrive.
If Columbia Gas crews are working in the area, contact them and the on-site project supervisor.